125TH Ave. Road Project

Road work beginning on May 12, 2025 ( as of 5-8-2025 start date of work is delayed)

  1. Work on taking hill down
  2. Culverts
  3. Ditching and widening road
  4. Pulverizing
  5. Paving

Scheduled to be a three-month project

Paving is to be completed by August 31, 2025

Final ditching/seeding will be down after that

Delays may happen due to weather

Continue to check the town website for updates